香港首座垃圾焚烧发电厂预计将于 2025 年底投入运营 || Hong Kong’s first waste-to-energy incinerator expected to begin operations by end of 2025
Lui said the department was aiming to commission tests early next year and expected the plant to begin full operations by the end of 2025.
I·PARK1, which costs HK$31.3 billion (US$4 billion) and took over seven years to build, is part of the government’s plan to stop relying on landfills by 2035.
The facility will be able to handle around 3,000 tonnes of waste per day, while reducing volume by 90 per cent after treatment.
Lui said construction of the incinerator’s chimney was more than half-completed, and the contractor was also carrying out work on the electrical and mechanical systems after 12 main modules had been delivered from its Zhuhai factory to the artificial island as of last month.
The process was not without its challenges, Lui added, as rough weather had affected transport of the modules, which weigh up to 6,000 tonnes each.
“In Hong Kong, we experience frequent typhoons from May to October, but can only do the delivery on a day with very good weather, weak wind and small waves.”
When the Post visited the facility near south Lantau on Wednesday, the main building that houses the incinerator was mostly completed, while generator modules for converting heat to electricity had yet to be installed.
The heat produced by the plant when it is fully operational will be able to generate the electricity needed for daily operations, as well as export an estimated 480 million kilowatt-hours (kWh) of power each year to the grid.
Lui said the department had made contingency plans to deal with inclement weather such as typhoons that could hinder the transport of waste to the plant.
“Poor weather will seriously affect the shipping of units of waste to the island,” he said, but in such as situation “a refuse transfer station in West Kowloon will be used to store the waste temporarily”. The waste will then be transferred to the plant after the typhoon.
He added that the island also had bunkers that could store waste for up to four days and that the incinerator would operate as normal even during inclement weather.
I·PARK2’s estimated daily treatment capacity could also be increased by 50 per cent from 4,000 to 6,000 tonnes, authorities said.
Once in operation, both plants will have a combined capacity to process 9,000 of the 11,000 tonnes of rubbish produced each day in Hong Kong.
Despite being situated on land, Lui revealed that the Tsang Tsui plant would rely on marine transport as its main way of receiving waste shipments.
“This will greatly reduce disturbance to residents who might be affected by refuse collection vehicles,” he said.
Lui said that once the two incinerators were up and running, the city’s waste processing methods would be aligned with international standards.
“Hong Kong is currently very reliant on landfills for waste disposal. That is considered backwards compared with the rest of the world.”
via News - South China Morning Post (author: Lo Hoi-ying)
Lui said the department was aiming to commission tests early next year and expected the plant to begin full operations by the end of 2025.
I·PARK1, which costs HK$31.3 billion (US$4 billion) and took over seven years to build, is part of the government’s plan to stop relying on landfills by 2035.
The facility will be able to handle around 3,000 tonnes of waste per day, while reducing volume by 90 per cent after treatment.
Lui said construction of the incinerator’s chimney was more than half-completed, and the contractor was also carrying out work on the electrical and mechanical systems after 12 main modules had been delivered from its Zhuhai factory to the artificial island as of last month.
The process was not without its challenges, Lui added, as rough weather had affected transport of the modules, which weigh up to 6,000 tonnes each.
“In Hong Kong, we experience frequent typhoons from May to October, but can only do the delivery on a day with very good weather, weak wind and small waves.”
When the Post visited the facility near south Lantau on Wednesday, the main building that houses the incinerator was mostly completed, while generator modules for converting heat to electricity had yet to be installed.
The heat produced by the plant when it is fully operational will be able to generate the electricity needed for daily operations, as well as export an estimated 480 million kilowatt-hours (kWh) of power each year to the grid.
Lui said the department had made contingency plans to deal with inclement weather such as typhoons that could hinder the transport of waste to the plant.
“Poor weather will seriously affect the shipping of units of waste to the island,” he said, but in such as situation “a refuse transfer station in West Kowloon will be used to store the waste temporarily”. The waste will then be transferred to the plant after the typhoon.
He added that the island also had bunkers that could store waste for up to four days and that the incinerator would operate as normal even during inclement weather.
I·PARK2’s estimated daily treatment capacity could also be increased by 50 per cent from 4,000 to 6,000 tonnes, authorities said.
Once in operation, both plants will have a combined capacity to process 9,000 of the 11,000 tonnes of rubbish produced each day in Hong Kong.
Despite being situated on land, Lui revealed that the Tsang Tsui plant would rely on marine transport as its main way of receiving waste shipments.
“This will greatly reduce disturbance to residents who might be affected by refuse collection vehicles,” he said.
Lui said that once the two incinerators were up and running, the city’s waste processing methods would be aligned with international standards.
“Hong Kong is currently very reliant on landfills for waste disposal. That is considered backwards compared with the rest of the world.”
via News - South China Morning Post (author: Lo Hoi-ying)